IOP Marina Public Dock and Greenspace

On September 22, 2020, City Council voted to create a public dock and greenspace in the space formerly leased to the commercial watersports operation. 

On November 2023, City Council awarded a contract to Truluck for the construction of a new public dock, which will include a 16' wide pier with covered area with benches and swings, a new floating dock with an ADA compliant gangway, kayak and stand-up paddle board launch. 

Construction began on April 2024, and the anticipated completion date is June 1, 2024. 


View the public dock design drawings here

Updates

Update - July 2024

Tuesday, August 13, 2024

IOP Marina Public Dock & Greenspace

  • Funding Source: $1.7M ($1M ARP, Marina Fund, Muni ATAX & State ATAX)
  • Framing and decking work complete. Gangway being fabricated. Truluck and ATM finalizing floating dock submittal.

 

Update - June 2024

Tuesday, June 18, 2024

IOP Marina Public Dock & Greenspace

  • Framing and decking work in process. Gangway and floating dock submittals under review by ATM - once approved, will be released for fabrication. City waiting on revised completion schedule.

IOP Marin "T" Dock Repairs 

  • Completed 

Marina Dredging - Design and Permitting

  • Work in process. ATM coordinating pre-application meetings and coordinating w stakeholder groups that are considering joining City's permit application. Construction anticipated in FY26.

 

Update - May 2024

Tuesday, May 14, 2024

OP Marina Public Dock & Greenspace

  • Funding Source: $1.7M ($1M ARP, Marina Fund, Muni ATAX & State ATAX)
  • Pile driving and superstructure construction almost complete. Delay on the floating dock and ADA gangway submittals, due in part to challenges with confirmation of location of subaqueous electrical cable that runs from the IOP to Goat Island near proposed floating dock. Substantial completion date is June 16th but may be pushed.

IOP Marina "T" Dock Repairs

  • Funding Source: $200K Marina Fund 
  • Repairs are near completion 

 

Update - April 2024

Tuesday, April 09, 2024

IOP Marina Public Dock & Greenspace

  • Funding Source: $1.7M ($1M ARP, Marina Fund, Muni ATAX & State ATAX)
  • Demolition of public dock began week of 4/1. After demolition, contractor will begin pile driving. Anticipated completion June 1st.

IOP Marina "T" Dock Repairs

  • Funding Source: $200K Marina Fund 
  • Work in progress 

Marina Dredging - Design and Permitting

  • Funding Source: $1.5M FY23 State Budget Allocation
  • Work in progress. ATM coordinating pre-application meetings and coordinating w stakeholder groups that are considering joining City's permit application. Construction anticipated in FY26.

Update - February 2024

Tuesday, February 13, 2024

IOP Marina Public Dock & Greenspace

Contract executed with Truluck Construction. Construction drawings in process. Contractor anticipated to mobilize in March.

IOP Marina "T" Dock Repairs

Removal of electrical and water systems, repairs to fixed pier and floatind dock and installation of fire extinguisher pedestals included in Truluck contract. Tenants requested to extend finger piers in lieu of new electrical and water systems, which requires permit modification from regulatory agencies. ATM provided proposal to City for permit modification assistance and coordination.

Marina Dredging - Design and Permitting

In process. ATM coordinating pre-application meetings and coordinating w stakeholder groups that are considering joining City's permit application. Construction anticipated in FY26.

Update - January 2024

Thursday, January 11, 2024

IOP Marina Public Dock & Greenspace

  • Construction contract executed and kick off meeting to be held end of January. Estimated project completion in May 2024.
  • Staff and ATM working on executing contract, then issue notice to proceed.

 IOP Marina "T" Dock Repairs

  • Budget for repairs approved by Council. Tenant feedback suggests a reallocation of funds away from replacing water and utility systems to extending finger piers. Permit modification required.

 Marina Dredging

  • In process. ATM, staff and marina tenants met in December to review scope and schedule. Also working with stakeholders who want to join City's permitting process.

 

Update - November 2023

Tuesday, November 14, 2023

IOP Marina Public Dock & Greenspace

Bid Package released on 10/19. Pre-bid meeting held on 11/1. Bid deadline
11/21.

IOP Marina "T" Dock Repairs

City received OCRM permit for minor repairs and maintenance for the "T" dock.
Scope of repairs included with the public dock project bid packet due 11/21.

Marina Dredging

In process. ATM completed the dredge disposal alternatives. Staff coordinating
progress meeting to review options and determine next steps in permitting
process.

Update- October 2023

Tuesday, October 10, 2023

Marina Public Dock & Greenspace 

Permits from Ocean and Coastal Research Management (OCRM) and the U.S. Army Corps (USACE) of Engineers are on hand.

IOP Marina "T" Dock Repairs

City reapplying for OCRM permit for minor repairs and maintenance for the "T" dock. City will bid scope of repairs with the public dock construction. In process.

Marina Dredging

ATM studying dredge disposal alternatives and preparing permit application. 

Update - September 2023

Tuesday, September 12, 2023

Public Dock & Greenspace 

Design work 95% complete. Permits from OCRM and USACE are expected by the end of September. Bidding will quickly follow once permits are in hand.

 

T Dock Repairs 

Repairs/Maintenance to the T dock to be included as an alternate bid with the public dock bidding process.

 

Dredging

City held stakeholder meeting on 8/23 to begin coordination with marina neighbors to join permitting and dredging efforts. ATM studying the dredge disposal alternatives.

 

 

Update - August 2023

Tuesday, August 08, 2023

Public Dock & Greenspace

• City needs to engage ATM for bidding and construction administration services.
• City and Islander 71 need to agree and finalize parking redesign plan for the north side of the boat ramp with the goal of eliminating
the shared lot and creating separate parking areas for the City/residents and restaurant patrons and finalize scope and design of the
greenspace along the landside of the boardwalk.


T Dock Repairs

Repairs/Maintenance to the T dock planned to be included as an alternate bid along with the public dock bidding process.


Dredging

Staff held kick-off meeting on July 18. First task involves local engagement and coordination with neighboring facilities on Morgan
Creek to identify their dredging needs and invite them to join City’s permitting efforts for potential cost and regulatory efficiencies.
Meeting with local stakeholders scheduled for mid-August.